Gunnison Valley Transportation Authority (RTA) Procurement Policies and Standards/Payments – Liquidated Damages Provisions

The Gunnison Valley RTA may use liquidated damages if it may reasonably expect to suffer damages (increased costs on project involved) from late completion and the extent or amount of such damages would be difficult or impossible to determine. In order to obtain liquidated damages, the Gunnison Valley RTA must suffer an actual loss. The amount of liquidated damages must be reasonable in light of the loss suffered. The assessment for damages shall be at a specific rate per day for each day of overrun in contract time; and the rate must be specified in the third party contract. Any liquidated damages recovered shall be credited to the project account involved unless the FTA permits otherwise.