SGR Master Condition Rating Definitions for RTD
This rating is based on how close an asset or component is to replacement or major overhaul.  Scores will not have a greater granularity than a half point.  An asset is in a State of Good Repair if the score is greater than (2.5).  Refer to individual asset group Inspection Standards Document for confidence in reliability and specific examples.
Confidence in Reliability = Remaining Useful Life
5.0) New or like new, 95% to 100% confidence in reliability; no visible defects, no damage, cosmetically looks new.  An asset is only new once, after rebuild some old parts are not new and therefore the highest score after rebuild is (4.5).
4.5)  The inspector is 90% to 95% confident in the reliability of the component / asset.
4.0) The inspector is 80% to 90% confident in the reliability of the component / asset. Shows minimal signs of wear, no major defects, and some minor defects with only minimal signs of deterioration.
Cosmetic defects/minor wear.
3.5)  The inspector is 70% to 80% confident in the reliability of the component / asset.
3.0) The inspector is 60% to 70% confident in the reliability of the component / asset. Some moderately defective or deteriorated components; expected maintenance needs.  Cosmetically “fair” but all devices are functioning as designed.
Small repairs or minor refurbishment.
2.5)  The inspector is 50% to 60% confident in the reliability of the component / asset.
2.0) The inspector is 40% to 50% confident in the reliability of the component / asset. Asset near overhaul or retirement, but in serviceable condition. Asset has increasing number of defects or deteriorated component(s).
Significant or multiple repairs needed.
1.5)  The inspector is 30% to 40% confident in the reliability of the component / asset.
1.0) The inspector is less than 30% confident in the reliability of the component / asset. Asset is in need of major repair or refurbishment, multiple minor defects or major defects.  Evidence of corrosion may be apparent; major or numerous minor areas of damage or structural issues.
Safety concern, critical damage, close to or time for overhaul or replacement. 
0)  Not safe to use, multiple major repairs or Asset set for disposal/retirement.